All work in the clean room engineering project: Note the 12 points mentioned below


All work content in clean room engineering: Note the 12 points mentioned below

(1) Use clean room dust-free cloth when cleaning walls in clean rooms;

(2) Configure the detergent with 90% deionized water and 10% isopropyl alcohol;

(3) In the clean room project , an approved clean room special detergent must be used;

(4) Check the garbage bins in the workshop and the preparation room every day and remove them in time.

(5) Every floor must be vacuumed. At each shift, the work should be done on the map, such as where it ends and where it starts.

(6), the floor of the clean room should use a special mop

(7) Use a special vacuum cleaner with a high-efficiency filter for vacuuming in the clean room.

(8) All doors need to be inspected and wiped dry

(9) Wipe the ground after sucking it. Rub the wall once a week.

(10) Vacuum and wipe under the raised floor.

(11) Wipe the pillars and support pillars under the raised floor once every three months.

(12) When working, you must remember that you will always wipe from top to bottom, and wipe from the direction farthest from the door.